| TL;DR If you want to move in by March, start choosing a designer this month. A realistic plan is: November for budget, references and designer shortlist; early December to finalise a designer and design; December to January for quotes, material selection and contract; January to February for execution; and late February to March for finishing and handover. Timelines depend on scope, so confirm dates in writing with your designer. |
Diwali is when many people finally decide to do up their home. Then the festival ends, the decision sits in a notes app, and three months later it is February and nothing has started. Interiors take longer than most people expect, mostly because of the decisions before work begins, not the work itself.
If you want to be in by March, the timeline below shows what needs to happen and when. It is a general guide for a typical full-home project and your actual dates will depend on scope, designer availability, material lead time and society rules.
Week 1 to 2 (mid November): Decide your basics
- Set a realistic budget range and keep a buffer for things you will not predict.
- List what you need versus what you would like. Storage, kitchen and bedrooms usually come first.
- Save 15 to 20 reference images, with notes on what you like about each one.
- Confirm your possession or move-out date and any society rules for interior work.
Week 3 to 4 (late November): Shortlist and meet designers
Speak to two or three designers, not ten. Ask to see completed projects, ask who will actually manage your site, and ask how they price their work (flat fee, per sqft or a percentage). Different models suit different projects, and it helps to understand the incentives behind each one. Visit a finished home if you can. Be cautious about any pressure to sign during a festive offer window.
Early December: Finalise the designer and the design
Once you have picked a designer, the layout is developed, followed by 3D views or detailed drawings. Do not rush this stage. Changes on paper cost nothing, while changes on site are expensive. Walk through the plan and ask where you will keep everyday items.
December to early January: Quote, materials and contract
- Get a detailed written quotation that lists materials, brands, finishes and what is excluded.
- Choose materials and finishes. Some items, such as certain tiles, hardware or imported fittings, can have long lead times.
- Agree a payment schedule linked to milestones, not just dates.
- Sign a contract that states scope, timeline and how changes are handled.
January to mid February: Execution

This is the on-site phase: civil changes, electrical and plumbing, false ceilings, carpentry and modular work. A full home generally takes a couple of months or more depending on scope, so keep some flexibility. Visit the site regularly, check progress against the agreed plan and raise issues early. Many delays come from late material orders and unclear decisions, so finalise choices on time.
Late February to March: Finishing and handover
Painting, polishing, lights, fittings, soft furnishings and final cleaning come at the end. Do a snagging walk-through with your designer, list small defects and agree a date to complete them before you move in. Keep the last payment tied to this.

Where timelines usually slip
- Starting the designer search too late in the year.
- Changing the design after execution has begun.
- Late selection of materials with long lead times.
- Society restrictions on working hours or material movement.
- Unclear scope in the original quote, leading to extra costs later.
Infrabob is built for the shortlisting stage in particular. We match Bangalore homeowners with verified independent interior designers and help you compare them. It costs the homeowner nothing, we do not take a share of your project value, and each designer sets their own prices, so you can ask every designer the same questions and compare like for like.
Frequently Asked Questions
When should I start if I want to move in by March?
Ideally by mid to late November, as the first month is spent on budget, references and shortlisting. Starting in December is possible but leaves less room for delays.
How long do home interiors usually take?
It varies with scope. A full home often takes a couple of months or more of on-site work after the design and contract stages. Ask your designer for a written timeline.
Is it a good idea to sign during Diwali offers?
Compare before you sign. Festival offers can create urgency, but the fit, the pricing model and the quality of past work matter more than a short-term discount.
How many designers should I speak to?
Two or three is a good number. More than that makes it hard to compare properly.
What should be in the quotation?
A line by line list of materials, brands and finishes, what is included and excluded, the payment schedule and the expected timeline.